Construction Schedule

Construction Schedule for the New Student Center at Salem College.

December 2012 – January 2013

Ground breaking

Installation of handicap accessibility ramp at Fine Arts Center parking

Site work – including installation of new side walk behind the science building leading to fitness center, The Cellar and Bryant Hall;  installation of temporary entrance to site at the rear of the dining hall

Utility relocation – steam, water, gas and electrical lines

February 2013

Continued site work, grading and utility installation

Building excavation and shoring

March – April 2013

Retaining walls, footings, underground plumbing, concrete (elevated slabs) 

May – June 2013

Set structural steel

Concrete slabs (other)

Roof dormer decking, framing

July – August 2013

Roof insulation, sheathing and dry-in

Sprinkler, HVAC, Plumbing

Framing and exterior wall sheathing

Brick Veneer

September 2013

Drywall

Electrical fixtures

Paint interior (partial)

October – November 2013

Drywall complete

Ceiling

Paint complete

Floor finishes

Kitchen equipment

December 2013 – January 2014

Auditorium seating

Final paint

Plumbing Fixtures

HVAC finishes

February-March 2014

Doors and hardware

Signage

Technology installation

Test and Balancing

Final Inspections

Commissioning

April 2014

Furnishings

GRAND OPENING!!!!!!!!​