New Student Center

Introducing the New Student Center at Salem College
Follow our progress on the
New Student Center Google Plus page and check out the construction schedule below.
 

Salem College will break ground on Tuesday, December 18, at 3 p.m. on a new student center.  The college’s Board of Trustees recently voted to proceed with construction, slated for completion in the spring of 2014.

This new facility will showcase a vibrant campus and act as a hub for student activity. The student center will feature a café, bookstore, theater, student lounge, meeting rooms and a student organizational workroom. Lambert Architecture + Interiors has designed the project that will be built by Frank L. Blum Construction to be modern and open while reflecting Salem’s historic roots. Located adjacent to Corrin Refectory and Bryant Hall, this will be the first new building erected on Salem’s campus since 1982.

"At Salem, our students are the heart of our mission. We are delighted that the new center will be located in the heart of campus and will provide a hub for student events and gatherings. It is especially appropriate that our newest building will pay tribute to one of our core values--community--and we look forward to generations of students and friends enjoying the new facility in the future,” says Susan Pauly, President of Salem Academy and College, who will speak at the ceremony along with individuals representing several partnering companies.


 
Lambert Architecture + Interiors
Frank L. Blum Construction Logo

Schedule

December 2012 – January 2013

Ground breaking

Installation of handicap accessibility ramp at Fine Arts Center parking

Site work – including installation of new side walk behind the science building leading to fitness center, The Cellar and Bryant Hall;  installation of temporary entrance to site at the rear of the dining hall

Utility relocation – steam, water, gas and electrical lines

February 2013

Continued site work, grading and utility installation

Building excavation and shoring

March – April 2013

Retaining walls, footings, underground plumbing, concrete (elevated slabs) 

May – June 2013

Set structural steel

Concrete slabs (other)

Roof dormer decking, framing

July – August 2013

Roof insulation, sheathing and dry-in

Sprinkler, HVAC, Plumbing

Framing and exterior wall sheathing

Brick Veneer

September 2013

Drywall

Electrical fixtures

Paint interior (partial)

October – November 2013

Drywall complete

Ceiling

Paint complete

Floor finishes

Kitchen equipment

December 2013 – January 2014

Auditorium seating

Final paint

Plumbing Fixtures

HVAC finishes

February-March 2014

Doors and hardware

Signage

Technology installation

Test and Balancing

Final Inspections

Commissioning

April 2014

Furnishings

GRAND OPENING!!!!!!!!​